New City Offices

City Offices Construction Update for January 31, 2021

Project Update

The final glazing & storefront is being installed in order to complete the building dry in. The upper-level canopy fascia and soffit installation have started with the remaining upper-level metal panels being completed. Mechanical, electric, and plumbing rough-in work is nearing completion with the uppermost level remaining. Crews are wrapping up drywall work with the project moving into the beginning of finishes installation starting on the main level.

On the Rio Grande Building, framing was completed and crews have started mechanical, electric, and plumbing rough-ins.

The elevator in the new building has been completed and crews have started work on the installation of the Rio Grande Building elevator.

The Aspen City Offices team is dedicated to public safety and the safety of construction crews and will continue to adhere to state and local COVID-19 operational recommendations and regulations as the situation evolves.

Coming Up

Installation of doors and hardware will start along with other finishes starting on the main level.

Crews will continue the installation of the storefront items, working on rough-ins. Drywall and insulation work is ongoing. Installation of doors and hardware will start.

Staircase Closure through summer 2021

The blue staircase connecting Rio Grande Place and the plaza (staircase east of the parking garage/plaza) is closed through summer 2021. For alternate access, use Jail Trail or the parking garage elevator.

View map >>

  1. About New City Offices
  2. Construction Information
  3. Project Financials
  4. Design and Site Plan
  5. Galena Plaza Outreach
  6. Stay Informed