Posted on: April 25, 2019

City Offices Rio Grande Pl. Road Closure Update

Media Contact: Kathleen Wanatowicz, Public Information

P: (970) 618-5114 | E: kathleen@prstudioco.com


Aspen, CO – April 25, 2019 – Right-of-way utility work from Mill St. to the west of the parking garage entrance is expected to be completed on schedule. During the week of April 29, crews will shift to the right-of-way utility work and the Rio Grande Pl. street closure to the east. Rio Grande Pl. will be closed from the east side of the parking garage entrance to Founders Place (east of Tasters Pizza).


Motorists are advised to be alert for parking garage access changes the week of April 29. Garage users will enter the parking garage via N. Mill St. (upper/west entrance) and will exit via Rio Grande Pl. (lower/north exit) to Mill St. There will be no access to the parking garage via Spring St. This section of road is expected to remain closed 24/7 until the beginning of June.


“Phase II, which includes new and upgraded utility infrastructure, is anticipated to wrap up in early June,” said project manager Robert Schober. “Construction will be on a hold during Food & Wine and will resume with building construction activities, including excavation, on Monday, June 17. The project is progressing nicely.”

 

Schedule and routes are approximate, weather dependent and subject to change. Business and pedestrian access remains open with some pedestrian detours in place. Please follow signage and flagger instructions.

 

Parking Closures

All street parking along Rio Grande Pl. is closed and will remain closed through the beginning of June. Expect periodic parking closures in several spaces in the Rio Grande Parking Garage during Phase II construction.


At this time no full closures of the parking garage or its north entrance are scheduled as part of city offices construction. However, based on site conditions, there may be periodic full closures of the parking garage.


Announcement from the Parking Department

As part of regularly scheduled annual parking garage striping a full garage closure will be required. The garage will close at approximately 6 PM on Friday, May 17 and is anticipated to reopen by 12 PM (noon) on Sunday, May 19. For questions please call the parking department at 970-920-5267.


Staircase Closures

The blue staircase connecting Rio Grande Place and the plaza (staircase west of Tasters) is anticipated to have intermittent closures. During closures, please use Jail Trail for access.


Intermittent closures of the west parking garage staircase (connecting the parking garage and housing/bank access) are anticipated. Additionally, the south sidewalk along Rio Grande Place remains closed, please follow detour signage. The north sidewalk (on the Rio Grande Park side) remains open.


At a later June date, construction activities will require a full closure of the lower section of the staircase (between Rio Grande Pl. and Parking Garage level 2). The date of this closure is to be determined, but the lower section of the staircase will close for the remaining duration of building construction, anticipated to be complete by summer of 2021.


Galena Plaza Public Space Connections | Public Process Update

Galena Plaza will play an important role in the long-term vision of enhancing the City of Aspen’s downtown connection with John Denver Sanctuary and the Roaring Fork River. Opportunities to engage in improvements to the public space connections around Galena Plaza will be taking place in June and throughout the summer. This effort will be led by the City of Aspen Parks and Open Space department. Sign up for “New City Offices” NotifyMe updates to receive updates on opportunities for involvement.

 

Save the Date: Neighborhood Meeting on May 8

The City of Aspen and its partners are holding an informational meeting on Wednesday, May 8 at 12 p.m. (noon) at the Pitkin County Library Dunaway Room for anyone interested in learning about the New City Offices project.  The project team will provide updates on project progress, schedule, work activities and impacts.


Public Information

Any updates will be announced via the City of Aspen’s New City Offices NotifyMe email and text alerts. Sign up for notifications at cityofaspen.com/NotifyMe.

Email: newcityoffices@cityofaspen.com

Webpage: www.cityofaspen.com/newcityoffices

24-Hour Hotline: 970-429-1793


Aspen City Offices Road Closure May-June 2019

 

Facebook Twitter Email

Other News in Press Releases

Aphid Season Nearing Conclusion in Aspen

Posted on: September 16, 2019

Tot Lot Playground Open House

Posted on: March 28, 2019

Groundbreaking for New City Offices

Posted on: February 5, 2019

2018 Aspen Citizen Survey Results Online

Posted on: January 25, 2019

City of Aspen Manager Resigns

Posted on: January 7, 2019

APCHA Rental Information

Posted on: December 5, 2018

Lift One Corridor Plan Open House

Posted on: November 19, 2018

City Ditches Shutting Down October 1

Posted on: September 27, 2018

2017 Aspen Citizen Survey Results Online

Posted on: December 4, 2017